Dev. Journal 04.26.23


On the 21st of April the voting of the Credits community about the changes in the project infrastructure ended, the overwhelming majority of community members supported the initiatives of the Credits team, from this moment began a new milestone in the development of the project.

Welcome to the latest edition of our Developer Journal. As we continue to build and enhance our blockchain project, we aim to provide regular updates and insights into the ongoing development process. The purpose of this journal is to keep our community informed, engaged, and excited about the progress we're making.


In the following article, you'll find a detailed breakdown of the key initiatives we are currently focused on, as well as the preliminary development timelines for each of these milestones. Our team is working diligently to improve the platform, ensuring it remains at the forefront of innovation within the blockchain space.

We appreciate the continued support from our community and look forward to sharing our progress with you.

So, let's go:


I Non-empty blocks CS blockchain

Preliminary development dates: from 10 April to 8 May

Tasks:

1. Consensus update for non-empty blocks selection 

(from 10 April to 24 April)

2. Blocks generation recovery in case when only non-empty blocks are stored 

(from 24 April to 1 May)

3. API update for node services with non-empty blocks 

(from 1 May to 2 May)

4. Monitor update to visualize non-empty blocks blockchain works 

(from 2 May to 8 May)


II Staking adjustment according to selected model

Preliminary development dates: (from 8 May to 5 June)

Tasks:

1. Adoption of build-in staking mechanics of node to selected staking model and parameters 

(from 8 May to 17 May)

2. Testing adjusted node 

(from 17 May to 5 June)

3. Monitor update to visualize staking parameters, statistic and profits 

(from 17 May to 29 May)

4. Web-wallet update to simplify dealing with staking 

(from 29 May to 5 June)


III Fee reduction for stakeholders

Preliminary development dates: from 5 June to 19 June

Tasks:

1. Development of dynamic fee 

(from 5 June to 12 June)

2. Testing dynamic fee 

(from 12 June to 19 June)

3. Monitor update to deal with dynamic fees 

(from 12 June to 15 June)

4. Web-wallet update to deal with dynamic fees 

(from 15 June to 19 June)


IV Solidity language introduction

Preliminary development dates: from 19 June to 24 July

Tasks:

1. Finalizing EVM module and CS node joints 

(from 19 June to 26 June)

2. Testing EVM module 

(from 26 June to 24 July)

3. Monitor update to work with solidity transactions 

(from 26 June to 3 July)

4. Web-wallet update to work with solidity transactions 

(from 3 July to 10 July)