Dev. Journal 04.26.23


On the 21st of April the voting of the Credits community about the changes in the project infrastructure ended, the overwhelming majority of community members supported the initiatives of the Credits team, from this moment began a new milestone in the development of the project.

Welcome to the latest edition of our Developer Journal. As we continue to build and enhance our blockchain project, we aim to provide regular updates and insights into the ongoing development process. The purpose of this journal is to keep our community informed, engaged, and excited about the progress we're making.


In the following article, you'll find a detailed breakdown of the key initiatives we are currently focused on, as well as the preliminary development timelines for each of these milestones. Our team is working diligently to improve the platform, ensuring it remains at the forefront of innovation within the blockchain space.

We appreciate the continued support from our community and look forward to sharing our progress with you.

So, let's go:


I Non-empty blocks CS blockchain

Preliminary development dates: from 10 April to 8 May

Tasks:

1. Consensus update for non-empty blocks selection 

(from 10 April to 24 April)

2. Blocks generation recovery in case when only non-empty blocks are stored 

(from 24 April to 1 May)

3. API update for node services with non-empty blocks 

(from 1 May to 2 May)

4. Monitor update to visualize non-empty blocks blockchain works 

(from 2 May to 8 May)


II Staking adjustment according to selected model

Preliminary development dates: (from 8 May to 5 June)

Tasks:

1. Adoption of build-in staking mechanics of node to selected staking model and parameters 

(from 8 May to 17 May)

2. Testing adjusted node 

(from 17 May to 5 June)

3. Monitor update to visualize staking parameters, statistic and profits 

(from 17 May to 29 May)

4. Web-wallet update to simplify dealing with staking 

(from 29 May to 5 June)


III Fee reduction for stakeholders

Preliminary development dates: from 5 June to 19 June

Tasks:

1. Development of dynamic fee 

(from 5 June to 12 June)

2. Testing dynamic fee 

(from 12 June to 19 June)

3. Monitor update to deal with dynamic fees 

(from 12 June to 15 June)

4. Web-wallet update to deal with dynamic fees 

(from 15 June to 19 June)


IV Solidity language introduction

Preliminary development dates: from 19 June to 24 July

Tasks:

1. Finalizing EVM module and CS node joints 

(from 19 June to 26 June)

2. Testing EVM module 

(from 26 June to 24 July)

3. Monitor update to work with solidity transactions 

(from 26 June to 3 July)

4. Web-wallet update to work with solidity transactions 

(from 3 July to 10 July)

Bizden e-posta ipuçları alın

HParanızı daha akıllı nasıl kullanırsınız./p>

Tıklayarak, Şartlar ve Koşullarımızı kabul etmiş olursunuz, Gizlilik politikası
Phone
Paranızı kolayca yönetin
Buraya tıklayın
İndirmek için tarayın

Credits.com finansı basit ve sınır tanımaz hale getiriyor. 2019’dan beri, her şey tek bir uygulamada: Bireylerin ve işletmelerin anlık para transferi yapmasına, birden fazla para birimini yönetmesine, ödeme kartları çıkarmasına ve profesyonel ödeme araçlarına zahmetsizce erişmesine yardımcı oluyoruz — evrak işleri yok, stres yok.

SECURITY AND EXCHANGE INTERNATIONAL CO INC. (No. 1001014352), Kanada Finansal İşlemler ve Rapor Analiz Merkezi (FINTRAC) nezdinde bir MSB (Para Hizmeti İşletmesi) olarak kayıtlıdır (MSB kayıt numarası: C100000279). Şirket, ödeme hizmeti sağlayıcısı olarak, para transferi, döviz işlemleri ve sanal para işlemleri gerçekleştirme yetkisine sahiptir.


Telif Hakkı © 2017-2025. Tüm hakları saklıdır.